Concrete bag chart

How many bags a hole or a pad takes, by bag size. Rounded up, because a job half a bag short is a second trip.

Concrete bag chart
PourCubic feet40 lb bags60 lb bags80 lb bags
10" hole, 3 ft deep1.64643
12" hole, 3 ft deep2.36864
4" slab, 3 × 3 ft3.001075
4" slab, 4 × 4 ft5.3318129
6" slab, 4 × 4 ft8.00271814

Reading it

  • A post hole holds less than the whole hole: the post takes up some of it. Subtract the post before you count bags.
  • Buy one more bag than the table says. Concrete you did not need is cheaper than a second trip mid-pour.
  • These are yields for standard bagged mix, as printed on the bag.